Silver Bridge Girder

AFHS TRADE CENTRE /

LOCATION

Cairns Airport

CLIENT

Hansen Yuncken

START DATE

August 2022

END DATE

October 2022

SCOPE OF WORKS

Construction of the AFHS Trade Centre

Terranovus Bridges was engaged by MSF Sugar to complete the remove and replacement of Steel Girders at Silver Bridge in South Johnstone.

Works included the Design and Construction of Temporary Crane Pads, removal and dispose of existing steel girders, Survey, Install new H/D Bolts and Grout Bearing Shelves, superstructure concrete remediations, Transport and Installation of 4 x 36m Steel Girders (70tn each).